Posted on 13 May, 2011 at 12:08 Comments comments (2)
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Hi everyone, all the tile hanging is now complete.  You can see from the second photo how i have weathered with the lead to the adjoining property.

Bromley gardens

Posted on 12 May, 2011 at 13:24 Comments comments (3)
Hi Everyone, I know that you can't see alot from this photo but we have felt and batterned all the outside.  We have also done all the lead work.  I will have better photos tomorrow of the tile hanging which should be finished.  Thanks

loft conversion Bromley Gardens

Posted on 7 May, 2011 at 15:09 Comments comments (149)
Hi everyone, As you can see from the photos we have been work hard.  From the top photo you can see that i have finished the frame work and i have boarded the outside and roof ready to felt.  The middle photo show that the floor joists are now in place ready to board after electrics and plumbing first fix.  The bottom photo shows i have created the stair well ready to cut through into the house.  Next job on the list is to 3 layer felt the roof and tile hang the dorma sides.  Thanks to everyone who reads my blog
Regards
Daniel

bromley loft conversion second blog

Posted on 4 May, 2011 at 14:52 Comments comments (14)
Here is the second blog with the work up to date.  I have fitted all the rafters, flitch beams, stud partions and dorma cheeks.  All have been inspected by the building inspector and passed. 

just started loft conversion in Bromley

Posted on 3 May, 2011 at 15:10 Comments comments (10)
Hi everyone,
               I have just started a loft conversion in Bromley with a L shaped dorma creating a master bedroom en-suite i will keep you all up to date with regular blogs and photos.  Here is some of what is completed to date: stripped the old roof,  fitted ridge beam, floor beams and just starting the dorma.  Tomorrow we will be fitting the roof beams and finishing the dorma.
 
 
 
 
 
 
 
 
 
I am waiting for finished photos of the refurbishment i have completed in station rd, Meopham should be getting them in the next few days.  I have also done a mansard roof conversion in Wimbledon since my last blog.
Regards
Daniel Bishop